Steinbach City Council · Jan 2022 – Sept 2026 · Highways PTH 12 and PTH 52
A bypass around Main Street? What council says and what the traffic study shows
Has Steinbach City Council considered a highway bypass that would take through traffic off Main Street (PTH 52) and Brandt Street (PTH 12)? What reasons has it given, does the city's own annual traffic study support them, and how have other Manitoba and Canadian cities handled provincial highways through town?
Bottom line
- Nobody is planning a bypass. Both highways are provincial, so a bypass would be the province's project. In 2018 the province called the idea “just a hypothetical concept”. Council has never moved, budgeted or asked for one at any meeting from 2022 to 2026.
- Council's reason is its traffic study. In February 2026 Councillor Jac Siemens said the yearly reports show “traffic comes to Steinbach, it doesn't go through Steinbach. So a bypass Doesn't make sense to me.” No other council member has argued for or against a bypass on the record.
- The study's numbers partly support him. In the 2024 evening peak, two-way traffic on Brandt St at the south end of the city was about 725 vehicles an hour. Mid-city on PTH 12 it was about 2,200. At Brandt St and Main St, only about 225 drivers an hour turned between PTH 52 West and PTH 12 North. That limits how much traffic can be passing through.
- But the study can't measure through traffic. It counts turns at 20 highway intersections for a few weekday hours. It doesn't record where trips start or end, and it doesn't report truck numbers. No origin–destination survey of Steinbach was found.
- Manitoba peers haven't built recent bypasses. Winkler, Morden and Niverville rebuilt their highways through town with the province, as Steinbach did at Loewen Blvd. Bypasses at Portage la Prairie, Brandon, Selkirk and Dauphin came with major provincial highway projects decades ago. Where Steinbach-sized cities have recently got one, such as Estevan in Saskatchewan, the province built it for heavy truck traffic. Yorkton measured its traffic with a licence-plate survey, found only 15% passing through, and put a bypass off. Steinbach has counted neither its through traffic nor its trucks.
Part 1 · The council record
Whose decision?
Steinbach's two through routes are provincial highways: PTH 12 runs north–south (PTH 12 North, then Brandt Street south of Main), and PTH 52 runs east–west (PTH 52 West, then Main Street). Manitoba Transportation and Infrastructure (MTI) owns them and runs every signal on them. A new highway around the city would be a provincial project; the city's part would be land-use planning, lobbying and possibly a cost share. For more on who controls what, see Traffic in Steinbach.
The only public bypass discussion by the province found for this report is from 2018. A highway access plan prepared by the province with the city and the RM of Hanover mentioned a perimeter highway or bypass. A provincial official said “the comment in that study is just a hypothetical concept being considered”. Asked whether anything was on the horizon, he said: “No, I don't see that happening anytime soon.” (SteinbachOnline, Mar 20, 2018). The province says that 2018 access management study of PTH 12 and PTH 52 led to a later design study for PTH 52 through Mitchell (EngageMB). Neither that study nor its September 2025 update, which the 2025 traffic study cites, is published online.
The city's 2025 development plan describes PTH 12 as “an Expressway north of PTH 52 and a Primary Arterial south of PTH 52”, and both highways as heavy-truck routes to be “preserved as major highway corridors”. The province's current five-year highway plan lists intersection improvements at PTH 12 and PTH 52 in Steinbach. It lists no bypass, realignment or twinning through the city (Manitoba 2025/26 infrastructure strategy, 2026–2030 list).
What the traffic study shows
Every year since 1997 the city has paid WSP Canada to count traffic on the two highways. The 2024 study, presented on March 18, 2025, counted 20 intersections on four weekdays in late September and early October 2024, from 3 to 6 p.m., plus a.m. counts at four sites (study, pp. 1–4). It is the main evidence council points to on the bypass question.
Where the traffic is
The map shows each stretch of PTH 12 and PTH 52 between two counted intersections, drawn wider the more traffic it carries in the weekday evening peak hour. Switch between the 2024 and 2025 studies, or split each stretch by direction. Tap or click an intersection to see where its traffic goes: how many drivers turned left, turned right or went straight, from each direction.
The interactive map needs JavaScript and an internet connection. The same numbers are in the tables below the map and in the chart that follows.
about 750 vehicles/hrabout 1,500about 2,250counted intersection (tap for turns)outermost counted intersection
northbound or eastboundsouthbound or westboundEach colour sits on the side of the road it drives on; wider = more vehicles.
Hover over or tap a stretch of highway.
Table of the map's stretch numbers
| Road | Stretch | 2024 | 2024 by direction | 2025 | 2025 by direction |
|---|---|---|---|---|---|
| PTH 12 | North Gate Dr → Clear Springs Rd | 1,875 | ↑985 ↓890 | 1,980 | ↑990 ↓990 |
| PTH 12 | Clear Springs Rd → Clearspring Centre / Golfair Rd | 2,015 | ↑935 ↓1,080 | 2,045 | ↑965 ↓1,080 |
| PTH 12 | Clearspring Centre / Golfair Rd → Park Rd | 2,220 | ↑1,050 ↓1,170 | 2,235 | ↑1,005 ↓1,230 |
| PTH 12 | Park Rd → Superstore / Co-op access | 2,150 | ↑1,030 ↓1,120 | 2,310 | ↑1,100 ↓1,210 |
| PTH 12 | Superstore / Co-op access → Acres Dr / Penfeld Dr | 2,190 | ↑1,055 ↓1,135 | 2,325 | ↑1,040 ↓1,285 |
| PTH 12 | Acres Dr / Penfeld Dr → Main St | 1,885 | ↑915 ↓970 | 2,055 | ↑1,065 ↓990 |
| PTH 12 | Main St → Woodhaven Ave / Friesen Ave | 1,470 | ↑725 ↓745 | 1,470 | ↑735 ↓735 |
| PTH 12 | Woodhaven Ave / Friesen Ave → Reimer Ave | 1,300 | ↑590 ↓710 | 1,350 | ↑605 ↓745 |
| PTH 12 | Reimer Ave → McKenzie Ave | 1,310 | ↑575 ↓735 | 1,345 | ↑565 ↓780 |
| PTH 12 | McKenzie Ave → Chrysler Gate | 1,015 | ↑415 ↓600 | 1,080 | ↑470 ↓610 |
| PTH 12 | Chrysler Gate → Madison Dr | 880 | ↑315 ↓565 | 925 | ↑360 ↓565 |
| PTH 12 | Madison Dr → Hanover Rd | 745 | ↑260 ↓485 | 825 | ↑325 ↓500 |
| PTH 52 | Westland Dr → Bushfarm Rd | 1,840 | →765 ←1,075 | 1,875 | →710 ←1,165 |
| PTH 52 | Bushfarm Rd → Keating Rd | 1,820 | →730 ←1,090 | 1,835 | →740 ←1,095 |
| PTH 52 | Keating Rd → Industrial Rd | 1,725 | →740 ←985 | 1,745 | →760 ←985 |
| PTH 52 | Industrial Rd → Lund Rd | 1,555 | →730 ←825 | 1,595 | →860 ←735 |
| PTH 52 | Lund Rd → Giesbrecht St | 1,730 | →860 ←870 | 1,570 | →825 ←745 |
| PTH 52 | Giesbrecht St → Brandt St | 1,680 | →860 ←820 | 1,630 | →810 ←820 |
| PTH 52 | Brandt St → McKenzie Ave / Hespeler St | 1,425 | →550 ←875 | 1,505 | →575 ←930 |
The chart below gives the same picture for 2024 at each intersection. It adds the two highway approaches at each counted intersection: northbound plus southbound on PTH 12, eastbound plus westbound on PTH 52. That gives a rough two-way flow on the highway at each point in the evening peak hour. Cross-street traffic isn't included. The highlighted bars are the outermost intersections the study counts on each route.
PTH 12 North / Brandt St, north to south
PTH 52 West / Main St, west to east
Counted intersectionOutermost counted intersection
| What the 2024 study found | Study says |
|---|---|
| Busiest intersection | Brandt St at PTH 52 West / Main St: 3,430 vehicles entering in the p.m. peak hour (Table 2.1) |
| Where corridor traffic peaks | “Combined traffic volumes … on PTH 12 North / Brandt Street peak at the Park Road West / East intersection” (p. 14) |
| Direction of the evening flow | On PTH 52 west of Giesbrecht St, “westbound traffic is generally higher than eastbound traffic in the weekday p.m. peak hour”. On PTH 12, northbound is higher than southbound in the south half of the city (p. 14) |
| Growth | Total traffic at all counted intersections fell slightly, 0.7% to 0.9% a year, over five-, two- and one-year horizons. Most 10-year intersection rates are positive, at 0.2% to 2.5% a year on PTH 12 (pp. 11–14, 30) |
| Construction | Loewen Blvd was closed during the 2024 counts and Park Road West just before the 2023 counts, so “some significant positive and negative one-year growth rates are to be expected” (p. 30) |
| Problem spots | Critical movements at PTH 52 and Giesbrecht St and at PTH 52 and Lund Rd operate at level of service F, the worst grade. Park Rd and Brandt at Main operate at overall level D; turning and cross-street movements at four PTH 12 signals are at F (pp. 30–31) |
| Recommendations | Signals at Giesbrecht St (already planned by MTI); keep monitoring Lund Rd and Industrial Rd; coordinate and re-time PTH 12 signals; add a protected eastbound left turn at Superstore/Co-op and at Brandt St and Main St (p. 31) |
| Bypass, through traffic, trucks | Not mentioned. Truck shares are used inside the traffic model but not reported, and the study doesn't record where trips begin or end |
The next study (WSP, January 2026), presented on February 17, 2026, shows the same shape. In its Table 2.1, two-way PTH 12 traffic at Hanover Rd at the south end was about 810 vehicles an hour, against about 2,330 at Park Rd. Two-way flow on PTH 12 now peaks “on the link south of the Superstore Access / Co-op Access intersection”. On PTH 52, “Traffic volumes west of Industrial Road have decreased slightly each consecutive year”. Traffic grew again overall: combined growth at all intersections was 3.3% over one year, 1.4% a year over two and 1.9% a year over five. The busiest intersection is still Brandt St at Main St, at about 3,465 vehicles an hour. The 2025 study's recommendations are about signal timing at Golfair, Park Rd and Superstore/Co-op, plus Giesbrecht and Lund Rd. Like the 2024 study, it says nothing about through traffic or a bypass (Feb 17, 2026 agenda, item 8A).
What the numbers can and can't say
A vehicle passing through Steinbach has to enter at one end of a highway and leave at another. On Brandt St, two-way traffic at the south end (about 725 an hour) is a third of the flow at Park Rd (about 2,200). So at most about 725 vehicles an hour in the evening peak could be travelling right through on PTH 12 from north to south. The real number is likely lower, because many of those trips start or end in the south of the city. Traffic also builds toward the middle of both corridors and falls off toward the ends, and westbound PTH 52 is heavier than eastbound in the evening, the pattern of people leaving jobs in Steinbach. Both fit Councillor Siemens's point that most traffic is coming to Steinbach.
The west end (about 1,800 an hour) and the north end (about 1,880) carry more traffic, and the obvious bypass route would link them. The study's turning counts help here. At Brandt St and Main St, 140 drivers an hour turned from PTH 52 West onto PTH 12 North and 85 turned the other way in 2024: 225 in all, under 7% of the 3,430 vehicles through that junction. In 2025 it was 180. Some drivers may cut through on Industrial Rd and Park Rd West instead. Even if every turn on that route were a through trip, the total stays below about 550 an hour in either year, and many of those trips are local. The 2024 study shows evening traffic heading out of the city in both directions: westbound on PTH 52 at Westland Dr (1,075) outnumbered eastbound (725), and southbound on Brandt St at Hanover Rd (485) outnumbered northbound (240).
The counts still can't follow a vehicle from one end of the city to the other. Only an origin–destination survey, which matches licence plates or tracks trips at points around the city, can. None was found for Steinbach.
What council has said and done
“Traffic comes to Steinbach”
“One, one of the things I always look at on this report is the amount of traffic coming into Steinbach and the amount of traffic leaving Steinbach, because I always get that, why isn't Steinbach building a bypass to help with the traffic? But we see when in this, these reports, we see every year when we do these, we see traffic comes to Steinbach, it doesn't go through Steinbach. So a bypass Doesn't make sense to me.”
Councillor Jac Siemens, on the 2025 traffic study · Feb 17, 2026 · 0:24:02
“The other thing is, this is always done in September or early October, this traffic study, and we're always under construction. The last quite a number of years we've been under construction at one of the intersections.”
Councillor Jac Siemens, same remarks · Feb 17, 2026 · 0:24:02
This is the only time in 103 regular meetings from January 2022 to September 2026 that a member of council spoke directly to the bypass question. Nobody responded to it, and council accepted the report unanimously (R26-037).
Using the study to lobby for intersections
“It helps us identify problem intersections or roads and it helps us to prioritize and get them up to speed to take the traffic that's coming through them.”
Mayor Earl Funk · Feb 15, 2022 · 0:25:42
“We have data that we're able to present to the province to show that our growth does does merit improvements to our intersections.”
Councillor Michael Zwaagstra · Feb 17, 2026 · 0:21:48
“And again, these recommendations are exactly that; they aren't they aren't must-haves.”
Troy Warkentin, City Manager, introducing the 2025 study · Feb 17, 2026 · 0:14:17
City streets as the bypass
In practice, Steinbach's “bypasses” are city streets that let drivers avoid the busiest stretches of PTH 12 and Main St: Park Road West, Acres Drive, Loewen Blvd and Old Tom Road.
“The traffic around Steinbach is horrendous.…And the traffic around Steinbach, when we paved Old Tom 10 years ago, whenever that was, there was a lot of unintended consequences, and that becomes a way to bypass Highway 12 and our main street.”
Councillor Jac Siemens · Sept 6, 2022 · 1:18:26
“One of the things that I did notice was that with Park Road being closed, Acres Drive has more than doubled in traffic.”
Councillor Jac Siemens, on the 2022 traffic study · Mar 21, 2023 · 0:45:46
“this is going to be a great bypass when we do the intersection at number 12 and Lowen Boulevard.”
Councillor Bill Hiebert, on the $1.97M Park Road West extension (SteinbachOnline reported the same words as his) · Mar 21, 2023 · 0:51:51
Residents living on those shortcuts have told council the cost. At a 2022 rezoning hearing, R.F., a Loewen Blvd resident, said: “It is already a major issue because these roads are being used as a city bypass and speedway and not designed to handle this.” (Sept 6, 2022, 1:00:58). In 2026, P.H. said of Friesen Ave: “Friesen has become like a major hub for truck transport to come down, although it is not a truck route.” (Jun 2, 2026, 0:40:27). Councillor Siemens answered the 2022 concerns by saying “There's not a definitive plan” for Old Tom and Loewen (1:19:40).
Trucks
“there will be more truck traffic on Main Street. And trucks generally go south on 12 or north on 12.…generally they're after the number 1 highway, they're going south to the border.”
Councillor Jac Siemens, on selling city land to a trucking company · Jan 16, 2024 · 1:31:02
Trucks are the usual case for a bypass, and the city's study doesn't report them. The province's most recent truck estimates (2019) put about 750 to 1,800 trucks a day on the PTH 12 sections around Steinbach, and about 500 to 1,235 on PTH 52 (MTI truck traffic layer). Those figures don't say how many trucks pass straight through. The city's designated truck routes are PTH 12 (Brandt St), PTH 52 (Main St), McKenzie Ave, Acres Dr and Industrial Rd (City of Steinbach), so through trucks are routed along Main St and Brandt St. In the 2024 discussion, staff confirmed that trucks serving that site would have to use PTH 52.
Follow-through
| Date | Action | Result |
|---|---|---|
| Mar 2018 | Provincial access plan for PTH 12 and 52 (with the city and RM of Hanover) mentions a perimeter or bypass | Province: “hypothetical concept”; nothing planned |
| Feb 2022 | Accepted the 2021 traffic study and sent it to the province with a request for signals at PTH 52 and Giesbrecht St (R22-038) | Signals switched on Oct 2026 |
| Mar 2023 | Accepted the 2022 study; asked the province to review its recommendations (R23-056). Awarded the $1.97M Park Road West extension as an alternate route | Park Road West built |
| Mar 2024 | Accepted the 2023 study and sent it to the province (R24-054) | — |
| Mar 2025 | Accepted the 2024 study and sent it to the province (R25-060) | Province reviewing signal timing, per staff |
| Nov 2025 | Loewen Blvd and PTH 12 intersection rebuilt with the province (about $11.2M; city about $6.1M) | Reopened Nov 24, 2025 |
| Sept 2025 | New development plan (By-law 2244) adopted; general land protection for future highway corridors | No bypass or ring-road corridor mapped |
| Feb 2026 | Accepted the 2025 study (R26-037). Unlike earlier years, the resolution doesn't say to send it to the province | Bypass dismissed in discussion; no motion |
| 2022–2026 | Any motion, budget item or letter about a bypass, perimeter road or origin–destination survey | None found |
Their reasons for not pursuing a bypass
1“Traffic comes to Steinbach, it doesn't go through”
Councillor Siemens's argument (above) is the only stated reason on the record. A bypass only helps if a meaningful share of traffic is passing through, so the reasoning is sound in principle.
The study's counts are consistent with it for north–south traffic, as shown above. But the study is a peak-hour intersection count, so it can't show how many drivers pass straight through. It doesn't count weekends, when shoppers from the region come in, or report trucks. Counts in recent years were also taken during construction, as Siemens himself noted. The claim may well be right, but the study wasn't built to prove it.
2It's the province's highway, and the province has no plans
“MTI, who is the authority who manages all the traffic signalization in Steinbach.”
Troy Warkentin, City Manager · Feb 17, 2026 · 0:14:17
Jurisdiction is real; the city can't build a provincial highway. But a city can still shape the option. It can ask the province for a corridor study, and it can keep a right-of-way open in its development plan so homes and businesses aren't built where a future route would go. Steinbach's new development plan (By-law 2244, adopted September 2025) has a general policy that “Land shall be protected for … any future highway system enhancements, such as interchanges, highway realignments, or new corridors”. But the only specific item it names is a realignment of PTH 52 at Bushfarm and Keating Rds. Its road map shows no bypass or ring-road corridor, and the words “bypass” and “perimeter” don't appear (Official Community Plan, pp. 13–16 and Reference Map 1).
3Build city connector roads and fix the intersections instead
“We've talked about that at our study sessions, and we continue to do that as part of our long-term planning process, is how do we manage our traffic flows within Steinbach.”
Councillor Jac Siemens · Sept 6, 2022 · 1:18:26
“I would hate to have 3 sets of traffic lights in one block”
Councillor Jac Siemens, on possible signals at PTH 52 and Lund Rd · Mar 18, 2025 · 1:33:18
This is the approach council has actually taken. It has added connector roads (Park Road West, Acres Drive), rebuilt the Loewen intersection, and lobbied for signal timing and the Giesbrecht lights. These steps serve local trips, the kind the study suggests dominate. The trade-off is that traffic moves onto residential streets such as Old Tom Rd, Loewen Blvd and Friesen Ave. Those streets don't get a traffic study unless a development affects PTH 12 or 52.
Part 2 · How Steinbach compares
Scorecard
Strong ahead of or matching good practice On par typical practice Partial started, with gaps Gap common elsewhere, not done here
| Measure | Steinbach | What others do | Rating |
|---|---|---|---|
| Highway traffic data | Yearly WSP count of 20 highway intersections since 1997, paid for by the city. | Few Manitoba cities of its size publish their own yearly counts; most rely on the province's highway counts. | Strong |
| Evidence on through traffic | No origin–destination survey; the bypass question is answered from turning counts. | Yorkton's province–city–RM study used a licence-plate survey (15% through) before deferring a bypass (2018); Lloydminster modelled bypass traffic in its 2016 master plan. | Gap |
| Rebuilding the highway through town | Cost-shared PTH 12 intersection upgrades (2014 fund; Loewen Blvd 2025). | Winkler twinned PTH 32 through the city; Niverville is rebuilding PR 311 ($17.65M, $9.65M provincial). | On par |
| City connector roads | Park Road West, Acres Dr, Loewen Blvd used as alternate routes. | Winkler built Northlands Parkway to ease a bottleneck in its north end. | On par |
| Protecting a future corridor | No bypass or ring-road corridor found in city plans; province calls it hypothetical. | Brandon's outer route (PTH 110) was built in stages from 1995 to 2013 on a planned corridor. | Gap |
| Keeping trucks off local streets | Truck routes on PTH 12 and 52; residents report trucks on Friesen Ave. | Brandon pairs a truck-route by-law with an outer provincial route. | Partial |
Key findings
1The bypass was dismissed, not studied
Council's only stated reason (reason 1) rests on a study that measures intersections, not trips. Its numbers make a large north–south through flow unlikely. Its turning counts suggest the west-to-north movement, the one a bypass would most likely serve, is also modest: at most about 550 vehicles an hour in the evening peak, and probably far fewer. But that's an upper limit worked out from turning counts, not a measurement. An origin–destination survey would answer the question directly, as Yorkton's did.
2Steinbach's approach matches its closest peers
The province controls the highways (reason 2), and no Manitoba city of Steinbach's size has had a bypass built recently. Winkler, Morden and Niverville, like Steinbach, are getting their highways rebuilt through town with cost-sharing. The bypassed cities, Portage la Prairie, Brandon, Selkirk and Dauphin, got them decades ago as part of larger provincial highway projects, not at a city's request.
3The real bypasses are residential streets
Choosing connector streets over a highway bypass (reason 3) has moved some traffic onto Old Tom Rd, Loewen Blvd and Friesen Ave, and residents there have complained. With the population projected to roughly double in 20 years (see Steinbach in 10 to 20 years), the city has no transportation master plan saying which streets are meant to carry that traffic.
4Elsewhere, bypasses follow trucks and crashes, and are measured first
In the Canadian cities that built one, the province planned and paid, sometimes with federal money. The trigger was usually trucks or safety rather than general congestion. Yorkton's truck route came with new canola plants and Estevan's bypass after truck traffic nearly doubled. Kenora's followed crashes on a Trans-Canada main street. Where through traffic was in doubt, the province measured it.
Yorkton is the closest match to Steinbach: a regional service centre of about 16,000 on several provincial highways. In 2016 its province, city and neighbouring RMs recorded licence plates on all seven highways into the area for 12 hours. “On average, 11,300 vehicles enter the study area on a highway each day, including 1,460 trucks. Of that number 1,700 vehicles (15%) including 475 trucks (32%) continued through the City”. The study concluded “it does not appear the through traffic demand on Highway 16 will warrant a high-speed through route” and recommended better regional connector roads instead (Yorkton Regional Transportation Study, 2018). That is Steinbach council's argument, settled with data, and it still found that a third of trucks were passing through.
In the small town of Moosomin, Saskatchewan, a two-hour provincial truck count at three points in 2016 found that “out of 83 vehicles, only 28 were through traffic”. The ministry “concluded that most Highway 8 traffic was destined for Moosomin, not passing through”. The town questioned how short the count was and asked for a fuller study (World-Spectator, Sept 7, 2016). That is the same argument Steinbach council makes, but tested by counting where vehicles went, and still disputed.
The research on effects is mixed. A 2005 study for New Jersey's transportation department reviewed earlier US and Canadian bypass studies. It found that rural bypasses “generally achieved their goal of diverting truck traffic out of downtown areas, but did not necessarily reduce overall downtown traffic volume.” It also found that “the building of a bypass road has little economic impact on the bypassed community.” One explanation it gives: once through traffic moves to the bypass, drivers who had been using parallel side routes return downtown (Rutgers Voorhees Transportation Center, 2005, executive summary and literature review). That supports council's view that a bypass wouldn't cure congestion caused by local trips. It also suggests the main case for one here would be trucks, which the city doesn't count.
Wisconsin's 1998 study of 17 bypassed communities points the same way. Origin–destination surveys in five of them found “an average of 76% of all vehicles having an origin or destination within the city or village”. In towns over 5,000 people, the old route lost only about 30% of its traffic in the long run, and “nearly all of the medium and larger communities have more traffic on their old highway route than on the bypass” (WisDOT summary). A Texas study found the reverse risk: “the better a relief route works from a traffic standpoint, the greater its adverse impact on local per capita sales” (Srinivasan & Kockelman, 2002). Florida's planning guidance says a bypass “may be appropriate where heavy truck traffic causes continuing unacceptable impacts” or “where a high percentage of trips are just passing through the community” (CUTR for Florida DOT, 2014). No Canadian or Manitoba standard sets a through-traffic share that justifies a bypass.
Peer municipalities
| Municipality | Highways and town centre | Source |
|---|---|---|
| Portage la Prairie, MB (13,270) | Bypassed: PTH 1 (Trans-Canada) runs around the city, built around 1968–70; the old route became PTH 1A (Saskatchewan Ave). The west overpass was replaced in 2021–24 | Manitoba; PTH 1A |
| Brandon, MB (51,313) | Bypassed: PTH 1 moved around the city in 1959. PTH 110 (Eastern Access Route), built in stages 1995–2013 for about $29.8M, links PTH 1 to PTH 10 for industry and trucks, alongside a city truck-route by-law | Manitoba; City of Brandon |
| Selkirk, MB (10,504) | Bypassed: PTH 9 runs around the south and west; PTH 9A carries the old route through town. The city has since rebuilt its main streets, adding $2.5M for turning lanes, medians and crossings on the provincial Main St in 2023 | PTH 9A; City of Selkirk |
| Dauphin, MB (8,368) | Bypassed: PTH 5 and 10 run around the city; PTH 5A/10A follow the old route through town (build year not confirmed) | PTH 10A |
| Winkler, MB (13,745) | No bypass: PTH 32, the main commercial strip, was twinned through the city with new signals (announced 2020) after 18+ years of city lobbying. PTH 14 runs along the north side, and the city built Northlands Parkway | Manitoba; Pembina Valley Online |
| Morden, MB (9,929) | No bypass: PTH 3 runs through the city south of downtown; council lobbied for signals and lower speeds at 1st St in 2023 | Pembina Valley Online |
| Niverville, MB (5,947) | No bypass: PR 311 through town is being rebuilt with four lanes, a roundabout and signals ($17.65M; $9.65M provincial), announced 2026 | Town of Niverville |
| Yorkton, SK (16,280) | Truck route, no full bypass: the province built a West Truck Route (2010–12, about $14M) for trucks serving new canola plants. A 2018 regional study by the province, city and two RMs then used a licence-plate survey. It found only 15% of vehicles entering on highways passed through the city (32% of trucks), so a full bypass freeway was left as a long-term stage only | Saskatchewan; Regional Transportation Study (archived) |
| Estevan, SK (10,851) | Bypassed: 13 km truck bypass opened 2015 ($45.5M: $28.5M provincial, $17M federal) after truck traffic rose more than 90% from 2007 | Saskatchewan |
| Kenora, ON (14,967) | Bypassed: Hwy 17A took the Trans-Canada off the main street, opened 1990 after 13 years of debate; the province redesigned entrances at residents' and businesses' request | Ontario Hansard |
| Lloydminster, AB/SK (31,582) | Planned: the 2016 transportation master plan recommends a Hwy 16 bypass, with a traffic model forecasting about 700 vehicles an hour in the peak direction. It tells the city to work with both provinces “to secure the bypass right of way” now | Transportation Master Plan |
| Cornwall, PE (6,574) | Bypassed: Trans-Canada bypass opened 2019 (about $65M). Weeks later the province said “80 per cent of truck traffic” was going around the town and business access was easier | CBC |
| Steinbach, MB (17,806) | No bypass: PTH 12 and 52 through the city; cost-shared intersection upgrades; bypass called “hypothetical” by the province (2018) | This page |
What “doing all it can” would add
- Ask the province for an origin–destination survey of PTH 12 and 52, on weekdays and a Saturday, with truck counts. This would replace the current inference from turning counts with an actual measure of through traffic.
- Publish the provincial access management plan (2018) and its September 2025 update, which shape where PTH 12 and 52 can be accessed and which roads may close.
- Publish the yearly WSP study on the city website, not only inside agenda packages, and keep sending each year's study to the province, as the 2026 resolution didn't.
- Settle the corridor question in the development plan. Either reserve land for a future ring road or highway corridor as the city grows north and west, or record a decision that the city doesn't want one.
- A transportation master plan that names which city streets are meant to carry cross-town traffic, so residential streets such as Old Tom Rd and Friesen Ave don't become bypasses by accident.
- Review truck routes using counts, and act on complaints about trucks on streets that aren't truck routes.
About this page
- Transcripts. Meeting quotes come from automatic transcripts of the official videos. The transcription often misspells the city's name; quotes show it correctly as Steinbach. Other words are left as transcribed (“Lowen” is Loewen). Each quote links to its moment in the video.
- Speakers. Quotes are from speakers identified with high confidence, except one. The March 21, 2023 “great bypass” remark was identified with medium confidence in the transcript as Councillor Bill Hiebert; SteinbachOnline's report of the meeting attributes the same words to him. Council members and city staff are named; residents are identified by initials.
- Traffic study. Study figures are from the 2024 Steinbach Annual Traffic Counting Study (WSP Canada, dated March 3, 2025), in the March 18, 2025 council agenda package. Page numbers are the study's own. The two-way flow figures in the chart were added up for this page from the study's Table 2.1. They are approach volumes, counted on different days, so they show the pattern, not exact traffic on each block. The 2025 study (WSP, January 2026) is in the February 17, 2026 agenda package; its Table 2.1 totals were added up from the approach columns because the PDF's table text is scrambled. The province's own daily highway counts weren't used, because station labels in its published tables couldn't be matched reliably to locations north or south of the city.
- Turning counts. The studies publish turning movements only as pictures (Figures 2.3 and 2.4: 2024 study pp. 8–9; 2025 study pp. 13–14). The numbers were read from those pictures. Every approach was checked against the study's Table 2.1, and all match within rounding except one: in 2025 the northbound movements at Woodhaven Ave / Friesen Ave add to 585, while Table 2.1 gives 605. The map shows both. The 2025 study's p. 14 figure is captioned “2024”, but its numbers are 2025's. The PTH 52 West to PTH 12 North figures are upper limits worked out for this page, not WSP findings.
- Map. Each stretch's volume is calculated from the studies' Table 2.1, as explained under the map. Highway lines come from Manitoba Transportation and Infrastructure's highway centreline layer. Intersection positions come from OpenStreetMap streets. North Gate Dr isn't named in OpenStreetMap, so it was placed using the spacing on the study's own map, and the Superstore/Co-op access was placed between the two stores. The background map is © OpenStreetMap contributors.
- Decisions. Resolutions were checked against the official minutes. Searches covered “bypass”, “perimeter”, “ring road”, “truck route” and “through traffic” in all 103 regular council meetings from January 2022 to September 15, 2026. Discussions in closed sessions or council planning sessions aren't public.
- Not confirmed. The 2018 provincial access study isn't published, so its bypass wording is known only from news coverage. The build years of the Selkirk and Dauphin bypasses, and who paid for them, weren't confirmed.
Sources
Council meetings (official YouTube recordings): Feb 15, 2022 · Sept 6, 2022 · Mar 21, 2023 · Jan 16, 2024 · Mar 5, 2024 · Mar 18, 2025 · Feb 17, 2026 · Jun 2, 2026
- Traffic study: WSP Canada, 2024 Steinbach Annual Traffic Counting Study (Project CA0041884.0650), in the City of Steinbach council agenda package for March 18, 2025, pp. 65–100; WSP Canada, 2025 Steinbach Annual Traffic Count and Analysis Program (January 2026), in the February 17, 2026 agenda package
- City: Official Community Plan, By-law 2244 (2025); Truck routes; Park Road West paving (SteinbachOnline, 2023)
- Provincial plans and data: Multi-year Infrastructure Investment Strategy 2025/26; 2019 truck traffic estimates and highway centrelines
- Map: Leaflet; background map and streets © OpenStreetMap contributors
- Province: No plans for a perimeter highway (SteinbachOnline, 2018); PTH 52 functional design background (EngageMB)
- SteinbachOnline: Traffic growing steadily (2017); 2023 traffic study; 2025 traffic study
- Research: Before-and-After Evaluation of Bypass Roads in New Jersey (Rutgers, 2005); Economic Impacts of Highway Bypasses on Communities (WisDOT, 1998); Srinivasan & Kockelman, Texas relief routes (2002); Bypass Basics (CUTR for Florida DOT, 2014); Moosomin traffic count (World-Spectator, 2016)
- Peers: see the peer table; populations from Census 2021 coverage
- Related reports: Traffic in Steinbach; Steinbach in 10 to 20 years